Supervision of Directional Conductors Driving
In October 2017 Trident completed the scope of work on technical supervision of assembling and driving of 9 conductors on the wellhead platform of Y. Korchagin field on behalf of the Client - “LUKOIL-Nizhnevolzhskneft” LLC.
The high point of the project was a successful driving of 1 vertical and 8 directional conductors to the depth of 80 meters below mudline by a dedicated contractor – CNGS Engineering LLC. Moreover, all 8 directional conductors have been driven within allowable azimuth range.