Supervision of directional conductors driving

In October 2017 specialists of Trident have completed scope of work on technical supervision of assembling and driving of 9 conductors on wellhead platform of Y. Korchagin field on behalf of the Client - “LUKOIL-Nizhnevolzhskneft” LLC.

 

The high point of the project was successful driving of 1 vertical and 8 directional conductors to the depth of 80 meters below mudline by dedicated contractor – CNGS Engineering LLC. Moreover all 8 directional conductors have been driven within allowable azimuth range.

More News
Company profile HSE Policy
IPM of Well Drilling Well Testing Services Subsea Services Reservoir Management Support consultancy
Pile Grouting Project in the Caspian Sea Integrated drilling project in the Sea of Azov for Priazovneft LLC Integrated Project Management of offshore well drilling Integrated well testing project for Cadogan Petroleum Plc Participation in well stimulation project Support services for GMC Limited Equipment rental contract IPM project for Transeuroenergy Project management of well drilling and testing on Subbotina field IPM of drilling and testing of TAT101 well on Tatyanovskoe field